Loadbank Operator Instructions
- Remove all transport covers completely before proceeding
- All loose materials that could block air intake to be removed away from unit while unit is testing
- Unit operates at very high temperature under load so all precautions should be taken to avoid exhaust air coming into contact with combustible material
- Unit should not be operated in areas where air flow is restricted
- Connect power cables to bus bars
- If supply is not 415V 50Hz an external supply is required to power the fans
- Set selector sw to internal/external supply as required. Sw located just below bus bars terminations
- Press fan start
- Before entering load make sure fans are blowing air across elements
- Follow instructions in the blue window
- Enter kW load and press enter
- For new load press reset, press the number of kW required and press enter
- Any mistakes when entering load will bring up instructions in blue window
- Follow instructions and resume test
- When load test is complete allow five to ten minutes to cool down fans
- Any problems contact Auspower EDM
- Unit will drop load off if temperature rises above a set level
- Allow unit to cool and resume test
Control All Units via the hand controlled 'combined'
- Connect all units together
- Make sure interconnection leads are connected male to female sockets. male to male will damage the unit
- Follow instructions in hand controller view window, combined load
Control all units via the hand controller 'individually'
- To enter load on individual units press view
- To enter individual loads on each unit press update and enter kW for unit selected
- Press view to go back to combined
|
|
|